·¬ÇÑÊÓƵapp

B836 Balliemore Bridge, Glen Lean - bridge now open

The B836 Balliemore Bridge, Glen Lean is open with a temporary bridge in place and work is being done to progress a new, permanent bridge.

The current situation

Conduit, provided by Openreach, has been installed at the temporary bridge. This enables Openreach to divert its cables from the exiting bridge to the permanent bridge. 

The design for the new bridge is complete and our contractor has confirmed that over the next three to four weeks, work will begin to demolish and remove the old bridge. Constructing the new bridge will begin in the New Year. 

Latest update on October 2023 weather event

The previous situation

After 7 October 2023, the council constructed a diversion road through a field to the north west of Balliemore Bridge, which allowed a temporary bridge to be placed slightly upstream of the existing bridge. The temporary bridge arrived onsite on 28 November and the road was opened safely on 1 December.

Image
Conduit has been placed along the temporary bridge

Conduit has been placed along the temporary bridge to carry the Openreach cabling.

 

 

Did you find what you were looking for?

Why wasn't this information helpful

Limit to 250 characters.